Quoted from Xerico:You are correct. Production Order is the most important.
My Production Number (i.e. Machine Number) is 127.
My Production Order started at 207. Skit-B moved it to 176 in August 2013.If 20 games can be built each month beginning in April 2014, mine would be built in the 9th month of production, which would be December 2014, And I'm fine with that timeline. (NOTE: I pulled 20 games out of thin air. The real number produced per months can only be provided by Skit-B)
1st Month -- April 2014 -- Machines 1 - 20
2nd Month -- May 2014 -- Machines 21 - 40
3rd Month -- June 2014 -- Machines 41 - 60
4th Month -- July 2014 -- Machines 61 - 80
5th Month -- August 2014 -- Machines 81 - 100
6th Month -- September 2014 -- Machines 101 - 120
7th Month -- October 2014 -- Machines 121 - 140
8th Month -- November 2014 -- Machines 141 - 160
9th Month -- December 2014 -- Machines 161 - 180
10th Month -- January 2015 -- Machines 181 - 200
11th Month -- February 2015 -- Machines 201 - 220
12th Month -- March 2015 -- Machines 221 - 240
13th Month -- April 2015 -- Machines 241 - 250Marcus
My brief discussion with Kevin about this is that they estimate it to be a bit quicker than that. I have faith they will get through them all by the end of the year if they indeed start in April.